A Trust in All but Name: Putting the Project Bank Account to Work
Photo: Richard Sutcliffe , CC BY-SA 2.0, via Wikimedia Commons
For most subcontractors, a main contractor's payment record is simply weather: something you forecast and endure. A project bank account (PBA) is one of the few mechanisms that changes the structure rather than the forecast. Instead of relying on the contractor's willingness to pass money down the chain, the money sits in a separate account, held on trust, from which you are paid directly.
That is a meaningful difference. It is also frequently misunderstood, and a PBA signed without scrutiny can create new timing risks in place of the old ones.
What a project bank account actually is
A PBA is not a separate company and not a conventional escrow. It is a bank account, usually held with a UK bank, operated by a trustee — commonly the employer or the main contractor, sometimes jointly — for the benefit of named beneficiaries. Those beneficiaries are typically the main contractor and a defined list of subcontractors, set out in a deed of trust or a set of PBA particulars.
The employer pays its assessed sums into the account. The trustee then pays each beneficiary directly, on the project's normal assessment cycle. Because the funds are trust property, they fall outside the trustee's estate if the trustee becomes insolvent. That is the whole point: the account routes around both the payment behaviour and the balance sheet of the party in the middle.
When you can expect one
There is no general statutory right to a PBA in England and Wales. The enabling provisions in the Enterprise Act 2016 have never been brought into force, so a subcontractor cannot demand one. In practice, PBAs appear in three settings:
- Central government construction. Departments commit, through Cabinet Office guidance, to using PBAs where appropriate, with thresholds commonly quoted in the region of £5 million. Exemptions exist and should be probed rather than assumed.
- Scotland. Policy has gone further, with PBAs expected on many public works contracts above a relatively low threshold.
- Private and regulated sectors. Voluntary, and increasingly used by clients who want tier-two stability on complex projects.
If a PBA is on offer, treat it as a benefit rather than an administrative inconvenience. If a public project above the stated threshold has none, ask why in writing before you price the work.
Five checks before you sign
1. Is it a trust in substance as well as in name?
Read the deed of trust. Is the account designated for the project alone, or can project money commingle with the contractor's working capital? Does the mandate require two authorised signatories? Is the trust properly constituted at the moment funds are paid in? A trust that exists only on the front page of a subcontract is worth very little.
2. Are you a named beneficiary, for the full value?
Confirm that your subcontract is scheduled, that the covered sum includes variations and, where relevant, retention (which is sometimes held in a separate retention account outside the PBA), and that the arrangement is adopted by reference in your subcontract. A deed of trust you have never signed is unlikely to help you.
3. Does the cycle actually shorten?
Model the dates rather than reading the prose. Employer assessment date, certification, employer funding deadline, trustee's payment date. A well-drafted PBA adds days, not weeks. Watch for drafting that allows the trustee to pay "within X days of receipt" while leaving the employer's funding obligation open-ended.
4. What happens when the account is not funded?
The trust protects you against the trustee's insolvency, not the employer's. If the account is empty, you are in a dispute about the assessment, and the PBA will not adjudicate it for you. Look for a stated position on non-funding, and satisfy yourself that your right to adjudicate is untouched.
5. Exit, closure and charges
Who closes the account, and when? How is any surplus dealt with at final account? Who bears bank charges? If you join the project late, do you benefit from funds already held? These are dull questions that become urgent at the wrong moment.
What a project bank account does not do
It does not resolve valuation disputes, cure defective applications for payment, or substitute for a performance bond or parent company guarantee. It does not protect you from your own errors in the payment application, which remain the most common reason a subcontractor is paid late.
It also does not remove the need for credit control discipline. A PBA still requires a compliant application, a dated record of what was submitted, and a diarised follow-up when the payment notice falls due.
A practical habit
Ask for the PBA documents at tender stage, not after award. A contractor that cannot produce them at tender is unlikely to produce a well-run account later. Where a PBA is genuinely in place, reconcile the account each month against your own applications, and keep the correspondence that shows the trustee's payment dates.
Prevention is cheaper than recovery. A PBA is not a cure for late payment culture, but on the right project it is the closest thing to a structural guarantee that a supplier can obtain without litigation, and it deserves to be examined as carefully as any other contract term.